Failure Factors of a Project

  1. Incomplete Requirements
  2. Lack of Executive Support
  3. Lack of User Involvement
  4. Lack of IT Management
  5. Lack of Resources
  6. Lack of Planning
  7. Change of Requirements or Specifications
  8. Don't need it anymore
  9. Technology illiteracy
  10. Unrealistic Expectations

Success Factors of a Project

  1. User Involvement
  2. Executive Management Support
  3. Clear Statement of Requirements
  4. Proper Planning
  5. Realistic Expectations
  6. Smaller Project Milestones
  7. Competent Staff
  8. Ownership
  9. Clear Vision
  10. Hard Working Focused Staff

What are common mistakes that the PM should avoid

  • We start coding without systematic problem analysis
  • We don't define requirements and quality goals
  • We don't follow and apply a process model
  • We set unrealistic deadlines
  • We use tools and methods we don't know sufficiently
  • We don't manage risks
  • We don't check project deliverables

What is a project?

It is a temporary endeavor undertaken to create a unique product or service

What are the characteristics of a projects

  • Temporary endeavor
  • Unique product
  • constrained by limited resources
  • Planned, executed and controlled
  • Have their own organizations
  • Performed by people

What are the kinds of projects

  • Order Projects
  1. done according to external clients
  2. Contracts define deliverables
  3. Disputes and conflicts are resolved in court
  • Internal Development Projects
  1. Clients and developers are within the same organization
  2. Product is used internally
  3. Conflicts are resolved by common top-level manager
  • Product development Projects
  1. The client is often the internal marketing division
  2. The product is offered and sold by the company
  3. The money is drawn from a global development budget


What is project management (PMBOK)

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements

What are the Tasks of Project Management

  • Project Organization
  • Team Management
  • Project Planning
  • Project Monitoring and Controlling
  • Stakeholder Management
  • Risk Management

What falls under Project Organization in the PM tasks

  • Define the Roles
  • Allocate responsibility and Authority
  • Setup Communication Structure for the project

What falls under Team Management in the PM tasks

  • Select People
  • Build the Team
  • Promote and motivate people
  • Solve Conflicts
  • Release the Team

What falls under Project Planning in the PM tasks

  • Define the goals
  • Analyze the environment
  • Structure the activities
  • Plan quality issues
  • Prepare the schedule
  • Estimate and plan resources
  • Plan cost and budget
  • Plan risk management

What falls under Project monitoring and controlling in the PM tasks

  • Measure the progress of the project
  • Activities to control the project

What falls under Stakeholder management in the PM tasks

  • Identify Stakeholders
  • Analyze interests and standpoints
  • Monitor interests and standpoints
  • Define actions to be taken

What falls under Risk management in the PM tasks

  • Identify Risks
  • Evaluate Risks
  • Define Mitigation and contingency measures

What are the skills of a project manager

  • Project Management abilities: Planning, estimation, controlling, time management, negotiation skills
  • Leadership abilities: communication, decision, delegation, motivation, moderation
  • Personal abilities: responsibility, toughness, team spirit, patience, faireness
  • Technical abilities: economical know-how, application know-how, software engineering know-how

What are the phases of Project management

  1. Initiation: Create business case, identify goals and risks, Identify Stakeholders, develop Project definition
  2. Planning: define scope, create project plan, set budget baseline, define roles and responsibilities.
  3. Execution: allocate and manage resources, develop product or service, meet often and fix issues.
  4. Monitoring and controlling: Track effort and cost, monitor progress, ensure adherence to the plan, Prevent disruption
  5. Closing: Handover and review deliverables, Document learnings


What are the objectives of the preparation(initiation) Phase

  • Provide all information needed to start the project: Involve Stakeholders
  • Define all Project Goals and Deliverables
  • Assess the project's goals and deliverables are they feasible, how is the return on investment.

What are Project Preparation Tasks

  • Define goals, objectives and deliverables
  • identify risks, assumptions and constraints
  • estimate cost and time
  • create the project definition document
  • Take the go/no-go decision

What is a project goal

A project goal is everything the project has to produce and to deliver. (The PM has to ensure all goals are achievable)

What is SMART?

SMART are properties for project goals:

  • Specific: What exactly is expected (accurate goals)
  • Measurable: Possible to measure progress
  • Actionable (Attainable): Possible to accomplish within the given resources
  • Relevant: In line with the company's goals
  • Time-Bound: Within a realistic time frame, and achievable until a target date

What are CLEAR properties of GOALS

  • Collaborative: Goals should encourage collaboration rather than competition
  • Limited: The scope of the goals should be limited to make them manageable
  • Emotional: Your goal should be emotionally important
  • Appreciable: Large tasks need to be broken down to make them achievable
  • Refinable: Goals need to be flexible to refine as new situations arise

What are the types of deliverables?

Tangible: Product, component

intangible: Increased reputation, recogntion, etc.

What is the difference between goals and objectives

Goals: High level statements that describe the overall context, should be in line with business goals.

Objectives: Fine grained or lower-level statements that describe specific actions or deliverables.

Flip to check the Hierarchy of project definitions

19529558566869467fb9efe8.76420874phpiohfomtn03q7czLfabq.png

What is a completion criterion?

Completion criteria are explicit deliverables that must be attained

What is the project definition?

is an overview document that sets the scope of the project.

What does the project definition entail

  • Project definition: Business objective or overall goal of project
  • Project Scope: Work of the project, it also entails duration, cost and impact on the organization. Also, objectives to be excluded.
  • Objectives: desired results and completion criteria.
  • Project deliverables: dates and deliverables

Who is a Stakeholder?

An individual, group, or organization who may affect, be affected by or perceive itself to be affected by a decision, activity, or outcome of a project.

What is Stakeholder Management?

Includes processes required to:

  • identify the people, groups or organizations that could impact or be impacted by the project
  • analyze Stakeholder expectations and their impact on the project
  • develop appropriate management strategies for effectively engaging stakeholders in project decisions and executions

What are the different attitudes of a stakeholder

  • Champion: Internal Stakeholder implementing the project and making sure everyone involved is on board and behind the ultimate success of the project
  • Promoter: External Champion
  • Sponsor: provides the needed resources and support for the project
  • Critic: Not completely convinced with the project and its goals
  • Opposition: tries to sabotage the project
  • Opposition leader: has the power to stop the project

What are the different power and interest classifications of a stakeholder?

778136100686970d6e81b01.06666684php2ilnhlmgmi8kcFbrdwC.png

If a stakeholder has high power and high interest how would a PM manage them

Positive attitude

  • Provide Information
  • Consult them before making decisions
  • Meet them
  • Encourage them to act as advocates

Negative attitude

  • Try to build trust that the project will be beneficial and the team will be able to do it
  • Find out what is important to them
  • Demonstrate that you are doing your best

If a stakeholder has low power and high interest how would a PM manage them

Positive attitude:

  • Maintain their enthusiasm and interest
  • Provide them with information
  • Involve them as much as the resources allow
  • Seek their input and opinion

Negative attitude

  • Do not waste time on them

If a stakeholder has High power and Low interest how would a PM manage them

  • Make sure that changes to the project do not increase the level of negative interest
  • Find out what is important and ensure that the project does not affect this
  •  If the project has a positive effect on them make sure they are aware

If a stakeholder has Low power and Low interest how would a PM manage them

  • Ensure they receive basic information
  • Invite them to presentations

What are Stakeholder Engagement levels

Leading: Aware of the project and actively engaged in ensuring its success

Supportive: Aware and in support of change

Neutral: Aware but neutral

Resistant: Aware of the project but resistant to change

Unaware: Unaware of the project and its impacts on them

What are engagement strategies with stakeholders

PPCP

  • Partnership: Include them in the project by inviting them to the decision-making progress in every step of the project
  • Participation: Find the areas that they are most interested in and entrust them with specific tasks or responsibilities
  • Consultation: Hold frequent consultations to make sure they remain supportive and to collect feedback that could help
  • Push Communications: Inform Stakeholders that may engage in your project later or are required by law to be informed

What are the steps of Stakeholder management?

  1. Identify Stakeholders
  2. Categorize Stakeholders: Attitude, Interest, Power, Engagement Level
  3. Map Stakeholders on Power Interest grid
  4. Create an engagement and communication plan
  5. Revise the plan based on feedback

What is Decision Analysis and Resolution (DAR)

a technique to analyze possible decisions using a formal evaluation process that evaluates identified alternatives against established criteria.

What are the steps of the DAR process

  • Plan the decision: Describe the decision issue and identify the stakeholders participating in the decision process.
  • Identify Alternatives: Involve stakeholders, brainstorm ...
  • Define Evaluation Criteria: Relevant differentiating factors
  • Select Evaluation method
  • Select Solution

Describe Pareto Analysis

Goal: Reduction of too many alternatives

  1. Collect the important selection criteria
  2. Rank these criteria
  3. calculate percentage of total and cumulative percentage for each criterion
  4. Align all criteria, sorted by their rankings in a row
  5. Select the subset of the most important criteria
  6. Narrow down the options and evaluate them based on the most important criteria

What is Paired Comparision Analysis

Goal: Determine relative ranking between alternatives (in pairs)

  1. List all pairwise Comparisions and compare and assign scores
  2. count the points


4160695236877f036886365.06901925phpcj4hro639jrvekgSXgK.png

Describe Grid Analysis

Goals: Select the best solution using Criteria Weights(Small number of alternatives)

  1. Define the Criteria and assign weights
  2. Rate each option for each alternative solution and calculate scores (W * S)
  3. Sum scores and select the preferred solution



16808164716877f084133937.05595660phpbrph4cskcb0bfdbnnpO.png

What are the different decision making approaches

  1. Directive: Team leader decides
  2. Consultive: Team leader decides after consultation
  3. Democratic
  4. Consensus

What is Project Planning

A continuous activity from initial idea to system delivery

What are the elements that should be planned

681648095686b84a9637dc5.28343079phpfd3tai51orqr0649MRa.png

What are the purposes of a project plan

  1. Guides project execution
  2. Provides a baseline for progress measurement and project control
  3. Documents assumptions, constraints, and goals
  4. Documents planning decisions regarding the alternatives chosen
  5. Facilitates communication among stakeholders
  6. Improves the efficiency of the operation
  7. Eliminates or reduces uncertainty

Define a Project Plan

A document that describes the technical and management approach to be followed for a project. 

Define the baseline of a project plan

The originally approved plan plus or minus approved changes

Baselines are used to:

  • compare the actual performance 
  • give forecasts of the project with the original plan

Define an activity

  • An element of work performed during the course of a project.
  • Define an expected duration, an expected cost, and expected resource requirements.

Define an atomic activity or work package

  • An activity that can be executed (by a single person or by a small group) within a short time
  • Delivers specified results that can be checked against their requirement

Define a milestone

Milestones are defined points in time during the project where defined results have to be available.

External Milestones:

  • Gate with a go/no-go decision
  • The “customer” decides based on the results and the market situation

Internal milestone

  • Milestone between external milestones
  • Used for internal controlling

Define WBS (Work Breakdown Structure)

A deliverable-oriented, hierarchical grouping of project elements that organizes and defines the total work scope of the project. 

84749191686b897c083c78.55870372phpbjjag3pmltt3bY5JFNY.png

How does the process of breaking down work looks like

2083612560686b89bd2c53b6.85887550php7ns58f61a4rn216WQWk.png

Define PBS (Product Breakdown Structure)

 The hierarchical structure of “things” that the project will make or outcomes that it will deliver

What are the rules for validation WBS

  • Disjunction rule: All activities of a level must be completely distinct
  • Completion Rule: If an activity is decomposed into sub-activities the whole scope of the activity must be covered

What are the questions that determine the checklist of a work package

  • Can we determine time and cost
  • Can we measure the progress
  • Can the tasks of the work package be performed independently from other work packages

What are precedence planning and temporal planning

  • precedence planning: defining the logical sequence of work packages
  • scheduling: defining the temporal sequence of work packages

What are the different activity planning techniques and their purposes

  • Milestone Chart: Rough Planning, Reporting
  • Bar Char: Planning, reporting, progress measurement
  • Activity Network Diagram: Detailed Planning, Reporting, Progress Measurement

What is the purpose of a milestone Chart

  • Defining the most important events of the project
  • A simple (but well-suited) communication means between customer and developer organization

What is the purpose of a Bar Chart

  • Like a Milestone chart
  • With end and start dates
  • Illustration of activities and milestones in an arranged graphical form
  • Communication tool between the customer and the project management

What is the purpose of an activity network diagram

  • Like Bar Chart
  • Shows workflow and critical paths
  • Dependencies of work packages

How do we create an activity network diagram

  1. Define Work Packages
  2. Define dependencies and duration
  3. create the network
  4. Calculate early and late start, early and late finish

Define total float of a work package

The time that a work package may be delayed or extended from its early start without delaying the project’s finish date

Define the free float of a package

The time that a work package can be delayed without delaying the early start of any immediately following work package

Name the steps of the delphi technique for effort estimation

  1. The moderator distributes the product/project definition to the estimators
  2.  Each estimator completes the estimation anonymously
  3. The moderator prepares and distributes a summary of the estimations together with unusual rationales provided by the estimators
  4. The estimators complete a re-estimation (again anonymously) based on the results of the previous round
  5. repeat as required

What are the advantages and disadvantages of the delphi technique

Advantages:

  • Simple and Cheap
  • Less biased than individual estimation
  • Team-based, iterative and collaborative
  • Does not require historical data
  • Works well with high level and low-level type estimations

Disadvantages:

  • Hard to find more than one estimator
  • Estimations difficult to reproduce
  • Can give fake sense of confidence

What are the steps of the wideband delphi technique

  • Team Selection: The project manager selects a moderator & an estimation team with 3 to 7 members.
  •  Kickoff Meeting: The first meeting during which the estimation team creates a draft WBS and discusses assumptions.
  • Individual Preparation: After the meeting, each team member creates an effort estimate for each task.
  • Estimation Session: The second meeting in which the team revises the estimates as a group and achieves consensus.
  • Assemble Estimate: After the estimation session, the project manager summarizes the results and reviews them with the team

What is planning poker

The agile variant of the delphi method, done with story points and playing cards

Procedure:

  •  Individual stories are presented for estimation.
  •  The story is briefly discussed.
  • Then each team member chooses from their own deck the numbered card that represents the estimate of how much work is involved in the story under discussion. 
  • All estimates are kept private until each participant has chosen a card.
  • At that time, all estimates are revealed and discussion can begin again

What is a story point

A unit used to estimate the difficulty of implementing a given user story.

What is team velocity

The average number of story points successfully implemented in sprints

What is the basic equation for effort estimation

Effort = Quantity * Quality / Productivity

Quantity: LOC, Function Points

Quality: Adjustment factors

Productivity: historical productivity data or business productivity data

What are the steps of function point analysis

  1. Define the system boundary
  2. Identify logical and user-identifiable data elements (ILFs, EIFs)
  3. Identify system operations (EIs, EOs, EQs)
  4.  Calculate the Unadjusted Function Points

What are the types of operations or transaction elements

External input (EI):

  • New data is entered, processed and stored
  • Returned status information is part of EIs

External Output (EO)

  • New data is created (e.g. reports)
  • Transferred to the user / other applications

 External Query (EQ)

  • Does not create data or change the data

What are the types of data or elements

 Internal Logical File (ILF):

  • Maintained and stored within the application
  • The data is needed by processes of the application
  • Grouping of data that forms a database table or an entity in the system

 External Interface File (EIF)

  • Maintained and stored by the environment
  • Design principles (e.g. information hiding) largely rule out the existence of EIF

Basic Data Blocks

  • Data Element Types (DETs): Attributes of a class, columns of a DB table, parameters, buttons
  • Record Element Types (RETs): DETs that are logically related and visible to the user

What is the basic program size formula for cocomo 2

 Example:

  • initially estimated program size: 3600 SLOC
  • 10% of the requirements will change
  • 1000 LOC can be reused (equals 200 LOC new code)
  • Size = (1 + 0,1) * (2600 + 200) = 3080
1269144069686bc2d0d591f3.72701175phpnp5skbvpjrap235pmvG.png

Define monitoring and controlling

  •  Track, review, and regulate the progress and performance of the project.
  • Identify any areas in which changes to the plan are required.
  •  Initiate the corresponding changes

What are the tasks of monitoring and controlling

Monitoring:

  •  Collecting project performance data
  •  Determining performance measures and forecasts
  • Reporting and disseminating performance information

Controlling:

  • Comparing actual performance with planned performance
  • Analyzing deviations
  •  Evaluating possible alternatives
  •  Taking appropriate corrective actions as needed

What are the goals of monitoring and controlling

Primary Goals:

  • Comparison of progress to the schedule and budgets
  • Creation of project status reports
  •  Analysis of the results and definition of appropriate control measures

Secondary Goals:

  •  Development of measurement procedures to assess actual project progress
  •  Establishment of monitoring and controlling standards
  •  Ensuring that the experience gained in projects can be used in follow-up projects

What is the goal of progress estimation

  • Delivering input data for plan/actual comparison
  •  Data has to be up-to-date to react to deviations early

What is Consequence analysis

  •  important task
  • analyzes deviations from the plan
  • defines and plans appropriate control measures

What are the types of control measures

  • Corrective measures: Closing the gap between the actual state and the plan
  • Plan modifications: Adapting the plan to the actual state of the project

What are examples of corrective measures

  • Schedule Adjustments: Reallocating tasks and fast-tracking, crashing (adding resources to the critical path)
  • Scope Management: Scope reduction or scope clarification
  • Resource Reallocation: training or hiring
  • Cost Control: cutting unnecessary costs and reassessing vendor contracts
  • Quality Improvements: stricter quality gates (cicd), Conducting code reviews and increasing test coverage
  • Communication Enhancements: more frequent meetings or stakeholder re-engagement

What is Milestone Trend Analysis

Technique to track how milestone dates shift overtime

What are the advantages and disadvantages of Milestone Trend analysis

Advantages:

  • very simple and intuitive (visual), does not require complex data 
  •  an efficient early warning system for schedule delays 
  • Can help in predicting future delays based on trends
  •  Project managers are actively involved in deadline monitoring.

Disadvantages

  •  MTA is not an objective measurement method
  • It is only effective if the participants work together in a spirit of trust
  • Does not provide sufficiently differentiated results for complex and large projects

What are the prerequisites of MTA

  • Defined milestones accepted by all important stakeholders
  • One responsible person per milestone
  • Early communication of milestone changes

Steps of MTA

  • Define Milestones
  • Draw the MTA Diagram
  • Obtain the forecasts of the milestone dates on the reporting dates!
  •  Analyze the trend lines and identify control needs!

What is Earned Value Analysis

A method to measure the amount of work actually performed and to forecast a project’s total cost and date of completion, based on trend analysis

What is Planned Value

The planned budget for the work that should be done until today

what is budget at completion BAC

The planned budget at the end of the project = PV(end date)

What is the actual cost

The total cost incurred for the project up to a specified date

What is the Earned Value

The sum of the planned cost for the work completed

Degree of completion * BAC

What is Cost Variance

Difference between the value of work performed and the actual cost

CV = EV - AC


Schedule Variance

Difference between the value of work performed and the planned costs

SV = EV - PV

What is Cost Performance Index (CPI)

Compares the value of work performed to the actual cost EV/AC

What is Schedule Performance Index (SPI)

Compares work performed to work planned EV/PV

What Estimate at Completion

Budget modified by current performance BAC/CPI

 The actual cost to date plus an objective estimate of costs for remaining work

Variance At Completion (VAC)

The final projected cost variance at the end of the project VAC = BAC - EAC

What is the To Complete Performance Index (TCPI)

The efficiency that must be achieved to complete the remaining work with the remaining money

161839208686c09a250d327.41063994phpgtgsv88mk58lesakrbD.png

What are the golden rules of EVA

  1. The earned value should be verified physically by examining the work product associated with the work packages!
  2. For unfinished work packages, earned value estimates are usually just a guess!

What are the advantages and disadvantages of EVA

Advantages:

  • clearly defined, simple, and fully traceable 
  • makes projects comparable with each other in terms of cost and schedule adherence
  •  It allows forecasts to be made

Disadvantages:

  • The complete implementation of the method is not easy
  • It requires an environment/organization with a high degree of project maturity
  • It is only applicable to projects with clearly defined requirements/ deliverables

What are the prerequisites of EVA

  • The project must be fully planned
  • The project must be structured into a sufficient number of work packages
  • Each WP must have a  cost estimate  a planned start date  a planned finish date
  • The effort recording must be structured according to the WP and must take place immediately

What is a Risk

An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objective.

What are the properties of a risk

  • Uncertainty
  • Likelihood
  • Consequence

What are types of risk classification, if classified according to the source of the risk

  • Organizational
  • Tool
  • Technology
  • People
  • Requirement
  • Estimation

What are types of risk classification, if classified according to the impact of the risk

  • Project: Schedule and resources
  • Product: Quality and Performance
  • Business: Organizations developing or selling the software

What is Risk Management

The process of identifying, analyzing, and responding to project risks. It involves also minimizing the consequences of adverse events on a project objective

What are the steps of Risk Management Process

  1. Risk Management Planning
  2. Risk Identification
  3. Risk Analysis
  4. Risk Response Planning
  5. Monitoring and Controlling
76855316686d28ba182279.29238807php3np3dq6d97pe4OE75A6.png

What is Risk Identification

  • Identify Project, Product and Business Risks
  • Defines a hierarchal structure: Class, Element, Attribute

What is the goal of Risk Analysis

  • identify Risks to be mitigated
  • Assess and prioritize identified risks
  • determine:
  1. Impact
  2. Probability
  3. Severity = Impact * Probability

Based on the severity of a risk, how should we respond

Very High: define and execute mitigation actions immediately

High: define and plan mitigation actions

medium: define mitigation actions

Low: Observe risks

What are the risk planning steps

  1. Establish Mitigation options
  2. Create Action Plans
  3. Re-evaluate risks
  4. repeat
732815968686d2af0145849.77845020phpghbtqrkk04qhdYls97t.png

What is the goal of risk response planning

Define and plan appropriate measure to manage risks.

What are the possible mitigation strategies

  • Risk Avoidance: change the plan to avoid risks
  • Risk Transference: Transfer all or part of the risk to another team
  • Risk Acceptance: Accept the consequences of the risk

There is also contingency plan, which is adding funds and resources in case the risk occurs

What are the parts of risk monitoring and controlling

  • Implementing, tracking and evaluating mitigation strategies and risk response
  • identifying new risks
  • Communicating Risks with Stakeholders
  • Every Major Risk has to be discussed at each project progress meeting
  • Reassessing risks to identify if the impact or the probability has changed

What are the benefits of risk management

  • Measures are planned and executed proactively
  • Risks are communicated explicitly
  • We can learn from former projects
  • Risks are identified and communicated clearly

What is a process

A series of actions that bring about a result

What is a software development process

 The process by which user needs are translated into a software product.

What is a software process model

  • an abstraction of similar software processes 
  •  a blueprint (a pattern) used to organize and perform a software process

What are the core elements of a software process model

Role responsible of activity is part of phase. Activity produces artifact that needs an activity

612134025686d7117285a66.71899234phpnrv95jr5ghl3dtKmG3K.png

What are Fundamental Development Approaches

Define basic procedures

  • to organize software development
  • without defining in detail activities, roles, and artifacts

define code and fix

a fundamental development approach where only coding, error correction and some ad-hoc testing are the activities done consciously

what is the waterfall model

A model of the software development process in which constituent activities, typically a concept phase, analysis phase, design phase, implementation phase, testing phase, and deployment phase are done in order, possibly with overlap but with little to no iteration

What are the problems with the waterfall model

It assumes that:

  • Requirements are known upfront before the design
  • Requirements rarely change
  • Users know what they want, and rarely need visualization
  • The system is not so complex

What is incremental development

WE don't develop the whole system, but we develop by increments, each increment implements is a defined user requirement. And project progress is not shown by documents but by executable systems

What is iterative development

 Controlled continuous revision of software, aiming at correcting errors early and integrating improvements

What is a prototype

A preliminary type, form, or instance of a system that serves as a model for later stages or for the final, complete version of the system

What are some special kinds of prototypes

  • Presentation Prototype: An initiation of the project. Usually made to convince a client that the future application system is either feasible or that its user interface and handling are in line with user requirements
  • Functional Prototype:  Is generally designed to illustrate specific aspects of the user interface or part of the functionality and helps to clarify the problem at hand
  • Breadboard: Only developer evaluate. Models a Critical Technical aspect of the final system

What are some approaches to prototyping according to Floyd

  • Exploratory Prototyping: Problem at hand is unclear
  • Experimental Prototyping: Focuses on the technical implementation of a development goal. 
  • Continuous Prototyping: It is a continuous process of adapting an application system to rapidly changing organizational constraints.

What are the main principles of the Agile Manifesto

  1. Individuals and interactions over processes and plans
  2. Working Software over comprehensive documentation
  3. Customer collaboration over contract negotiation
  4. Responding to change over following a plan

What is agile development?

Software development approach, based on iterative development, frequent inspection and adaptation, and incremental deliveries, in which requirements and solutions evolve through collaboration in cross-functional teams and continuous stakeholder feedback

What are the values of extreme programming

  • simplicity
  • communication
  • Courage
  • Feedback
  • Respect

What are the roles in XP

  • Customer: Part of the team, takes business decisions
  • Developer: Every member on the team, realizes the stories
  • tracker: Often a member of the team, collects relevant metrics for progress measurement
  • Coach: usually an external consultant that has worked with xp before and is there to mentor the team

what are the prerequisites for xp

  • The development team is not distributed
  • All developers communicate with each other
  • The programming language allows one to write readable code
  • The customer is available throughout the projects
  •  Developers, managers, and customers are convinced of XP

benefits of xp

  1.  Changing requirements are handled
  2.  A useful system version is developed very early

cons of xp

  • Lack of central and important documents
  • Traceability ⚫ Changing requirements and new design decisions imply modified and new test cases
  • Test cases have to be maintained very well

what is scrum framework

iterative project management framework used in agile development, in which a team agrees on development items from a requirements backlog and produces them within a short duration of a few weeks

What are the values of scrum

  • Commitment  Team members personally commit to achieving team goals
  • Courage  Team members do the right thing and work on tough problems.
  • Focus  Concentrate on the work identified for the sprint and the goals of the team.
  • Openness  Team members and stakeholders are open about all the work and the challenges the team encounters
  •  Respect  Team members respect each other to be capable and independent.

What are the principles of scrum

  • Transparency  Each team member is aware of the other team members
  • Inspection  Frequent inspection points allow the team to reflect  Daily Scrum Meeting and the Sprint Review Meeting
  • Adaptation  The team constantly investigates how things are going and revises those items that do not seem to make sense

what are the scrum events

  •  Sprint Planning  Negotiation between the product owner and the team about the set of features to be realized in the next sprint  The effort is estimated by the team
  • Daily Scrum
  • Sprint Review  Presentation of the realized features to the product owner  Acceptance/ rejection decision for each feature of the initial sprint backlog
  •  Sprint Retrospective  Are there improvement potentials for forthcoming sprints?

What are the roles in scrum

  • Product Owner  represents all stakeholders  knows requirements (business and technical)  maintains product backlog  decides what to develop next (during the next sprint)  accepts or denies realized features
  • Scrum Master  ensures that the scrum process is performed as intended  supports the team and the product owner  supports the team in improving its process and competencies
  • Development Team  self-organized interdisciplinary team  estimates development effort for each feature  there is no team leader

What are the artifacts of scrum

  • Product Backlog  contains all product features and changes  technical and non-technical ones  estimated by e.g. story points or person-hours/days
  • Sprint Backlog  contains features to be developed in one sprint  determined in the sprint planning meeting  more detailed than the product backlog
  • Product/Release Burndown & Sprint Burndown  serves to monitor sprint progress and the project’s progress
  •  Release Plan  defines the number of sprints and delivered working releases

what is scrum of scrums

A technique to scale Scrum up to large groups (over a dozen people), consisting of dividing the groups into Agile teams of 5-10.

What is Nexus Frame work

All teams (the Nexus) work on the entries from a common product backlog in their sprints.  The goal is to produce a common integrated product increment at the end of each sprint  Nexus extends the elements of Scrum so that they can be used at the level of all teams

What is the Kanban method

A means to design, manage, and improve flow systems for work